Can't force check in a Project - Projext 2007 RRS feed

  • Question

  • We have a user that can't check in a project that he has had checked out for nearly a month.  I've tried to do a force check in, but we get this error

    Your ProjectCheckIn job failed.  Its current state is Failed.  It was 37% complete.  It entered the queue at 09/30/2011 08:23:24.
    
    To get more information about the job failure, please go to Project Web Access.  Select Personal Settings from the left menu.  Then select My Queued Jobs.
    
    The errors returned from the queue are as follows:
     Error ID: 3116
     Error ID: 23008
     Error ID: 26000
    
    Detailed error below - send it to the administrator for more detailed troubleshooting.
    
    <?xml version="1.0" encoding="utf-16"?>
    <errinfo>
      <general>
        <class name="Status approval internal error">
          <error id="3116" name="StatusingInternalError" uid="63b6aeae-44fb-4017-a928-b608dd828bf8" />
        </class>
        <class name="Object reference not set to an instance of an object.">
          <error id="23008" name="ProjectCheckinFailure" uid="30521dd1-7e9a-4c6b-823c-196e222a67bc" ProjectUID="7b8d2b94-e9b8-40e5-91e3-1bbb2b777da6" JobUID="7a4cb7ad-cf54-4d37-843c-206ea07c2e00" MessageID="4" Error="System.NullReferenceException: Object reference not set to an instance of an object.&#xD;&#xA;   at Microsoft.Office.Project.Server.BusinessLayer.StatusApprovalMessageHandler.ProcessingComplete(StatusApprovalApplyResult result, StatusApprovalMessageHandlerResult status)&#xD;&#xA;   at Microsoft.Office.Project.Server.BusinessLayer.StatusApprovalMessageHandler.Process(StatusApprovalMessage message, StatusTransactionState expectedState, Boolean keepSchedulingResults, StatusApprovalApplyResult&amp; result)&#xD;&#xA;   at Microsoft.Office.Project.Server.BusinessLayer.StatusApprovalMessageHandler.Process(StatusApprovalMessage message)&#xD;&#xA;   at Microsoft.Office.Project.Server.BusinessLayer.StatusApprovalMessageHandler.ApplyInProcessStatusApprovalsForProject(Guid projectID)&#xD;&#xA;   at Microsoft.Office.Project.Server.BusinessLayer.Queue.ProcessProjectCheckinMessage.ProcessProjectCheckinApplyStatusUpdatesMessage(Message msg, Group messageGroup, JobTicket jobTicket, MessageContext mContext)&#xD;&#xA;   at Microsoft.Office.Project.Server.BusinessLayer.Queue.ProcessProjectCheckinMessage.ProcessMessageCallback(Message msg, Group messageGroup, JobTicket jobTicket, MessageContext mContext)" />
        </class>
        <class name="Queue">
          <error id="26000" name="GeneralQueueJobFailed" uid="169bd4ac-59c1-4b26-bf22-0f04d62c4aa9" JobUID="7a4cb7ad-cf54-4d37-843c-206ea07c2e00" ComputerName="HOMER" GroupType="ProjectCheckIn" MessageType="ProjectCheckinApplyStatusUpdatesMessage" MessageId="4" Stage="" />
        </class>
      </general>
    </errinfo>
    
    

    I'm not quite finding any deatils searching around the net.  Is there any way I can get this checked in or get it out of the checked out queue?

    Friday, September 30, 2011 1:52 PM

Answers

  • Hi Paul,  At 37% during the check-in job the project is applying any updates.  The best approach would be to check for any recent updates that are pending - if the PM is the only PM then he may be able to see these on his Approval Center history page.  Hopefully that may give a clue the the failure - but it appears to be finding a NULL value when it is not expecting to.  Perhaps some data changed in the background while this update was wating to be applied.

    If you can't work out what happened then opening a support incident may be the best approach - and we can then help identify what is up with the update.

    Best regards,

    Brian.


    Blog | Facebook | Twitter | Posting is provided "AS IS" with no warranties, and confers no rights.
    Project Server TechCenter | Project Developer Center | Project Server Help | Project Product Page
    Monday, October 10, 2011 6:18 PM
    Owner

All replies

  • Hi there,

    Are there any jobs for this project that are not complete yet? Change the job history to go back to the last time this project was editted and refresh the queue.

    Thanks

    Paul


    Paul Mather | Twitter | http://pwmather.wordpress.com
    Friday, September 30, 2011 2:02 PM
    Moderator
  • I went back 2 months, not showing any data in the queue that far back though.  The checkout that I can't force in is nearly a month old.

    His local cache in project shows nothing under either filter as well.

     

     

    Monday, October 3, 2011 12:06 PM
  • If the project isn't in his local cache, what happens when he tries to retrieve and open it from the server?  It may give a warning, but this may allow him to open it, close it, and check it back in.
    Terrie T - MCTS - PMP - MBA****PMO & Project Server Admin
    Thursday, October 6, 2011 3:25 PM
  • Hi Paul,  At 37% during the check-in job the project is applying any updates.  The best approach would be to check for any recent updates that are pending - if the PM is the only PM then he may be able to see these on his Approval Center history page.  Hopefully that may give a clue the the failure - but it appears to be finding a NULL value when it is not expecting to.  Perhaps some data changed in the background while this update was wating to be applied.

    If you can't work out what happened then opening a support incident may be the best approach - and we can then help identify what is up with the update.

    Best regards,

    Brian.


    Blog | Facebook | Twitter | Posting is provided "AS IS" with no warranties, and confers no rights.
    Project Server TechCenter | Project Developer Center | Project Server Help | Project Product Page