none
Project 2013 and Earned Value Analysis with additional baselines RRS feed

  • Question

  • Hi,

    I have been able to use the Earned Value analysis tools for my original baseline, but want to now run Earned Value against Baseline2. I am getting zeroes for SPI, BCWS, etc. I have saved Baseline2. And for that matter I get zeroes for Baseline1, also saved.

    Any thoughts on what I am missing?

    Thanks,

    cs

    Monday, June 20, 2016 2:16 PM

Answers

  • Hi,

    In the project options, go to file/options, advanced section, scroll down to the "earned value options for this project" group of options and select the baseline 2 as the baseline used for EV calculation.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    Monday, June 20, 2016 2:57 PM
    Moderator