Material Resouces Driving Duration RRS feed

  • Question

  • How can I get Material Resources to drive duration? For example, if I have a resource call "External Wall" that I have work of 1000 lm to manufacture, how to I assign a productivity rate of 10lm/hr so the duration automatically calculates at 10 hours?
    Saturday, September 10, 2016 6:34 AM

All replies

  • Hi,

    In your case, I'd suggest to use a work (eventually generic) resource, since it is generating work/duration.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    Monday, September 12, 2016 7:12 AM