none
Graphical indicator problem in PWA RRS feed

  • Question

  • First: I defined a custom task field in Project Server 2010, the field is numeric with some graphical indicators, later I created a
    Project and make some updates to this filed in several tasks, then I published and review the project in PWA and the graphical indicators works very well (I
    also created a view that contains the indicator).<o:p></o:p>

    Then I modified the task field definition in PWA using minimum value for resume task and project summary task, then I edit the
    previous project and tested the modifications in Project Professional 2010 and all works, the values for resume task and project summary task was right. But
    when I published the project to Project Server, and review the indicators in the same view the values for resume task and project summary task was the not updated.<o:p></o:p>

    I think that Project Server is not calculating the minimum value and I don´t know why, Can somebody help me?<o:p></o:p>

    Thanks in advance

    Wednesday, February 27, 2013 1:39 AM

All replies