MSProject 2007 the use of filter to get only a range of free Slack listed in a a column question RRS feed

  • Question

  • Hi,

    I am wondering if someone can help me write the command for getting only the tasks that have a free Slacks ranging from e.g. 3 and 7 Days? this Free Slack has already been integrated into the project Plan in a column. I tried to use a formula but did not work. In this column called Free Slacks may contains value variying from Negative values (-) to any Positive numbers.

    Looking forward to hearing from you and thanks in advance!

    Chuck

    Thursday, August 9, 2012 11:06 PM

Answers

  • Hello Chuck,

    I believe the following filter definition will do it:

    Regards.

    • Marked as answer by chamdan Friday, August 10, 2012 9:10 PM
    Friday, August 10, 2012 12:38 AM

All replies