Decimal Numbers in Work field in Project Server 2013 RRS feed

  • Question

  • Hi,

    I have a project in Project Server 2013(MPP),in which; for few summary tasks the hours are shown in decimal(like 19.02hrs in Work field- in duration field, value is whole number but in the work field it shows decimal value).

    But all of the below subtasks are whole number.

    May I know how to resolve that?


    K.Gokulraj

    Wednesday, July 15, 2015 10:13 AM

All replies

  • Hi

    Check that you don't have a milestone under the summary task that is not 100%. Often people mark the tasks as complete and forget the milestone, so the summary isn't right.

    If that doesn't work check the assignment level (Resource Usage or Task Usage) to check there isn't an incomplete assignment.

    If that isn't it you could look at any settings in File...Options...Schedule to check that there isn't some setting that isn't calculating properly.

    Good luck

    Ryan Darby

    www.ipmo.com.au