Adding Field to Deliverable List on Project Site RRS feed

  • Question

  • How do I add resource names to the Deliverables List on the Project Site in Project Server 2010, Sharepoint 2010?
    Monday, June 16, 2014 1:25 PM

All replies

  • Hi Tom, 

    As far as I know, you cannot add by configuration the default resource name field in the deleverable list of the project site. You might code some custom code to retrieve this information, otherwise you'll have to create a new "person or group" column in the list to manually add the resource name.

    Note that you can add the modified by and created by column.


    Hope this helps,


    Guillaume Rouyre, MBA, MCP, MCTS |

    Monday, June 16, 2014 2:26 PM
    Moderator
  • Guillaume,

    Thank you for the comment.  I will not institute custom code into our system in case future updates could cause issues.  I will keep watching for any comments that offer a standard way to do this without customizing the system.

    Tom


    Monday, June 16, 2014 4:49 PM
  • Guillaume,

    I am back to address this further.  What columns can I add to the Deliverables List on the project site?  How is this done?

    Thank you!

    Friday, February 13, 2015 7:03 PM