  • Hello,

    We have a template with the summary task enabled. Both in "Design" and in "Options > Advanced > View option for this project > All new project".

    The template is published to Project Server and is attached to the right EPT.

    The next step is to create a new project with this saved template.

    When I open this project in MS Project the Summary task is still disabled.

    In the Gantt Chart view on the Project Server, the summary task is enabled and visible.

    Does anyone has any idea what went wrong?

    We have Project Server 2013.

    Thank you in advance,

    Mark Klerkx

    Tuesday, December 10, 2019 2:24 PM

All replies

  • Hi Mark,

    First I would check that you don't have any filter active in MS Project, so the project summary task migh be hidden.

    Then I would try to apply the option not only to "all new project", but also to the template file, before saving it as a template.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller