Want to see a delay in resource engagements. RRS feed

  • Question

  • I have a project where on several tasks internal as well as external vendor resources are assigned. Sometimes vendor resources start the tasks at later date while internal resource start based on the task start date. I want to run a report where I can see delayed starting on a task by vendor resources and how many days delay.
    Thursday, May 1, 2014 6:26 AM

Answers

  • Firstly, in the resource sheet in Group column you can add Vendor or Company name to those resources. Secondly, you can go to resource usage and create a new Group by, first filter on Group (which will differentiate between vendor and internal resources) than by Assignment Delay (this will show on which task vendor resources lead to delayed start. Hope this helps.


    Sapna Shukla

    Thursday, May 1, 2014 6:55 AM
    Moderator