In PWA, the cost and actual cost are shown as 0 instead of the negative number RRS feed

  • Question

  • Hi,

    There are two tasks assigned to resource “Credit – Labor” which is a material type and has standard rate as -1.

    In Project Professional the actual cost shows correctly as (unit*standard rate) which yield a negative total, therefore the credit;

    In PWA, the cost and actual cost are shown as 0 instead of the negative number. I have cross checked the Reporting  database in  MSP_EpmAssignmentByDay and MSP_EpmAssignmentBaselineByDay] i can see the negative values in both these tables.

    But when i verify the same in MSP_ASSIGNMENTS_WORKING_VIEW in Published database i can see 0 as value instead of negative value.

    Can any body help me on this.

     


    Geeth If you feel that the answer which i gave you is Helpful please select it as Answer/helpful.