Hi Team,
We are configured Mirroring & Logshipping in 3 servers 01-02 is mirroirng and 01-03 Logshipping
in 01 we have taken 01 server cloning the same in 02 & 03 also
01 is Principal server here we have maintaince jobs here its working succesffully
in 03 also the same maintaince plans is there here some of sub plans are failing due to some reason
My Question is :
In Maintaince plan we have some backups full, -t-log, Re-build index etc..
in full and T-logs backups are failing every day.
The same data is only in 03 also why we need Maintaince plan in 03 ?
because in 01 mirroing,logshipping and full & T-log backups are going to good.
Can you please suggest in 03 server what action we have to take can i remove the maintaince backups or it will continue please suggest me.
Thanks
subu