Project Server 2010 - Actuals do not consistently overwrite Planned work when submitting through timesheets RRS feed

  • Question

  • We are having inconsistencies of planned work hours not being overwritten by actual hours that are submitted through timesheets.  There is sometimes a fractional number difference between the actuals and work hours, yet, the majority of the time, the actuals will overwrite the plan (which apparently is the norm).  My preference is that the actuals overwrite all of the planned hours and that any other task with planned hours in the resource time sheet would become 0 if not worked.  This issue requires quite a bit of effort for our PMs to go back into the plan to ensure that all actuals match planned, and make a correction to the planned hours to match the actuals if needed.  Does anyone else have this issue?  Is there a way to configure Project Server to do this.  Thanks!
    Tuesday, March 10, 2020 7:44 PM