  • i entered a task in ms project then its start when i entered the actual start the ms project split the task automatically

    why did it do that?????? 

     
    Friday, August 12, 2016 12:41 PM

Answers

  • the problem still going on despite of I deleted the the predecessor 
    • Marked as answer by Abd.Alhamad Saturday, September 3, 2016 7:35 AM
    Saturday, August 13, 2016 11:33 AM
  • Does it have progress on the task ( %complete > 0)? Is it possible that there are tasks that are higher priority assigned to the same resource?

    By the way, it helps if title of the post is more descriptive. Cheers!

    • Marked as answer by Abd.Alhamad Saturday, September 3, 2016 7:35 AM
    Monday, August 15, 2016 11:39 PM

All replies

  • If the task has a predecessor and it finishes later than the actual start you entered, then the task will split as the remaining duration still obeys the split. you can delete the predecessor link and the task split should disappear.

    Rod Gill
    Author of the one and only Project VBA Book
    www.project-systems.co.nz

    Saturday, August 13, 2016 5:49 AM
    Moderator
  • the problem still going on despite of I deleted the the predecessor 
    • Marked as answer by Abd.Alhamad Saturday, September 3, 2016 7:35 AM
    Saturday, August 13, 2016 11:33 AM
  • Does it have progress on the task ( %complete > 0)? Is it possible that there are tasks that are higher priority assigned to the same resource?

    By the way, it helps if title of the post is more descriptive. Cheers!

    • Marked as answer by Abd.Alhamad Saturday, September 3, 2016 7:35 AM
    Monday, August 15, 2016 11:39 PM