none
Project Server 2007 - Project Center - '% work complete' column data not getting updated RRS feed

  • Question

  • In Project Server 2007, Project Center's " % work complete" , "Actual Work" data is not getting updated whenever we update our tasks using "My Tasks". Do we need to do anything else to update these columns automatically?
    Friday, July 23, 2010 5:10 PM

Answers

  • Hello Sanjeev,

    The projects have to be updated and published for that data to be updated. 

    MIchael WHarton, MBA, PMP, MCT


    Sincerely, Michael Wharton, MBA, PMP, MCT, MCSD, MCSE+I, MCDBA www.WhartonComputer.com
    • Marked as answer by Sanjeev S K Friday, July 23, 2010 6:22 PM
    Friday, July 23, 2010 5:43 PM
    Moderator