none
All tasks showing 0H remaining . RRS feed

  • Question

  • Hello

    We are using project server 2010 with SharePoint 2010 and user is complaining that “0h remaining” is still showing up on time sheet  from the aged entries. Below are  few entries from the long list of tasks all showing remaining work 0. Any help with this? Thanks .  

    Project: Project Name

     

    Below are the latest schedule changes. Contact your project manager if

    there are any problems with the changes.

    Your work assignments below have changed.

      Task Name: task 1

      Start: Tuesday, January 11, 2011  Finish: Thursday, January 13, 2011

    Work: 6h  Remaining Work: 0h  % Completion: 100

     

      Task Name: task2

      Start: Monday, January 17, 2011  Finish: Monday, January 17, 2011

    Work: 0h  Remaining Work: 0h  % Completion: 0

     

      Task Name: task3

      Start: Monday, January 17, 2011  Finish: Monday, January 17, 2011

    Work: 0h  Remaining Work: 0h  % Completion: 0

     

      Task Name: Task4

      Start: Thursday, February 10, 2011  Finish: Thursday, February 10,

     2011

     Work: 0h  Remaining Work: 0h  % Completion: 0


    • Edited by UMAR_USNT Thursday, June 30, 2011 2:03 PM typo
    Thursday, June 30, 2011 1:57 PM

All replies

  • Hi Umar,

    EPM Administrator can control the view that any task owner can view the future tasks for any specific time period and the incomplete tasks in the past using the Task Display settings / Timesheet Advanced settings in the server settings. If SEM (Single Entry Mode) is on, then you have to check both the settings.

    Thanks,

    Raj


    Thanks, Raj
    Friday, July 1, 2011 9:41 AM