BCWS Calculation Issue RRS feed

  • Question

  • Hi All,

     

    We created a 3 day test project on the 365 server (Project Server 2016). It has single task (task1) and one resource with std. rate $120/hr. Details as below –

    Baselining is done for the same dates. On the day 2 of the project, we expect BCWS $960 ($120*8 hrs). However, in task pane, below is observed.

    In Project page, however, correct values were shown.

    Today, on day 3, however I see both task and project pages showing same values.

    Friday, June 3, 2016 7:44 AM

All replies

  • Hi,

    When you edit the project schedule PDP, you see the draft version of the project; whereas when you are in the project center, you see the published version on the project. This might explain the discrepency.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    Friday, June 3, 2016 8:52 AM
    Moderator
  • We have tried with Published version also but no result . Also if project opened in Project Pro & then published on Project Online/Project server then also we are unable to see changes..
    Friday, June 3, 2016 9:25 AM