MS Proj 2013: Task split doesn't show as "....." RRS feed

  • Question

  • When a task is split, either manually or by using the "Incomplete Parts to Status Date" function, the task in the Gantt chart shows a longer 'bar' instead of the normal dotted line indicating the split. I've checked the Bar Styles menu; splits are shown properly. The button for "Split Tasks in Progress" under the Project Options/Schedule menu is 'checked'. Not sure where else to look for an issue. Thoughts?

    Thanks!

    Chris

    Thursday, May 25, 2017 1:05 PM

All replies

  • Hi Chris,

    It may be that someone has changed your bar styles for this chart.  Worth using the Reset to Default button for the view and see if this displays the split correctly.   Read the warning before resetting to default. 


    Ben Howard [MVP] | web | blog | book

    Thursday, May 25, 2017 3:17 PM