ProjectServer_Reporting.MSP_WssDeliverable on Project Server 2010 RRS feed

  • Question

  • It is possible to insert some new fields into the ProjectServer_Reporting.MSP_WssDeliverable? Without broken any thing!

    Sorry for the newbie question, but I had to ask.

    Wednesday, December 4, 2013 8:45 PM

Answers

  • Hi,

    Though it may not break anything at the moment, changing the table design in any the Project Server database is undesirable for the reason that application of future patch will remove or break it. It may also break the upgrading/migration of data to a future version if there is a need.

    Thursday, December 5, 2013 2:43 AM