  • B73UTV,

    Let's say the night shift starts at 11:00PM on Saturday and finishes at 7:00AM on Sunday.

    1. Go to Project > Properties group > Change Working Time

    2. In the Change Working Time window, click on the Work Weeks tab in the lower half and then click on "Details"

    3. Set up the two days as shown:

    4. If you want to extend a night shift sequence, use the following setting

    Hope this helps.

    John


    Wednesday, August 9, 2017 1:27 PM
  • Have a look at https://support.office.com/en-gb/article/Create-a-new-base-calendar-674cb99d-f2b0-4e85-b07e-84105d540dcb (found by Google search "create calendars in microsoft project")