Timescale in Deliverable page (Project Online) RRS feed

  • Question

  • Hi,

    Is it possible to change the timescale : Years and Months instead of Weeks and Days in the Deliverable page (PWA)

    Thanks


    • Edited by WLID1966 Monday, August 31, 2015 1:56 PM
    Monday, August 31, 2015 1:53 PM

Answers

  • WLID1966 --

    Unfortunately, I have never found a way to change the timescale units on the Deliverable page of any Project Site, so I suspect there is no way to do this.  I have found this to be quite frustrating at times, unless you really enjoy scrolling left and right!  Hope this helps.


    Dale A. Howard [MVP]

    • Marked as answer by WLID1966 Friday, September 4, 2015 7:31 AM
    Thursday, September 3, 2015 9:28 PM
    Moderator

All replies

  • WLID1966 --

    Unfortunately, I have never found a way to change the timescale units on the Deliverable page of any Project Site, so I suspect there is no way to do this.  I have found this to be quite frustrating at times, unless you really enjoy scrolling left and right!  Hope this helps.


    Dale A. Howard [MVP]

    • Marked as answer by WLID1966 Friday, September 4, 2015 7:31 AM
    Thursday, September 3, 2015 9:28 PM
    Moderator
  • Does this applies for other views of Project Online as well? e.g. Gant Chart of Project Centre, ...?
    Wednesday, March 9, 2016 1:35 PM
  • Nasser --

    No, you can use the Zoom In and Zoom Out buttons in the Project Center to change the timescale.  Hope this helps.


    Dale A. Howard [MVP]

    Wednesday, March 9, 2016 3:03 PM