Where do I find booking type in my project schedule? RRS feed

Answers

  • Ankit --
     
    Display the Build Team from Enterprise dialog and then add at least one enterprise resource to your project team.  You will see a column for that team member called Booking, which is where you specify the Booking Type value for that particular resource on the project.  Your choices are Proposed and Committed.  Hope this helps.

    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Friday, March 2, 2012 7:59 PM