How to costrain leveling so that a resource is never assigned to another task until its current one is finished (stick resources to a single task until it is finished) ? RRS feed

  • Question

  • Hello,
    I am really puzzled with the resource assignments and auto-leveling feature.

    If I assign a resource to 2 tasks which are not linked together (i.e. they do start at the same day), when levelling project (professional 2013) tipically levels the resource so that it works 5 hours on the first task and the remaining 3 on the second one.

    As you know you can't move someone from a task to another every day, thus what I want to achieve is that, due to the assignment, the resource is never split between the two tasks, but rather that one of the task is delayed until the resource finishes the other task.
    I want project to consider a resource "sticky" to a task until the task is completed.

    How can I achieve this?

    Thanks in advance