none
Time scale of Gantt chart RRS feed

  • Question

  • Hello,

    When i put an activities and deliverables in the ms project, the gantt chart time scale shows dates that are before the 1st task and so as beyond the last task in the project. Is there a way to restrict gant chart time scale to specific dates etc? I am using MS Project professional 2010 as desktop application.

    I will really appreciate if anybody can help on this.

    regards,

    Haroon


    Haroon


    • Edited by shah123 Sunday, May 17, 2015 4:57 PM
    Sunday, May 17, 2015 4:55 PM

All replies

  • Haroon,

    First, I'd check to insure the Project Start date is the same as the earliest task in your plan. Look under Project/properties group/Project Information. If's that okay then to limit the timescale to just the project span, go to view/zoom group/zoom/zoom and select the option to show the "entire project".

    Hope that helps.

    John

    Sunday, May 17, 2015 5:08 PM