  • Question

  • When I inactivate a task, I would expect the RAG status to be green or blue and not show up on the dashboard as red as that task is no longer relevant.  However, it shows overdue - how do I correct this? I thought I could mark it 100% complete and then deactivate but this is not possible. Also, I do not want to delete the task as I use my plan for several projects, in some the tasks will be needed and I don't want to risk missing them for future projects.

    Many thanks

    Tuesday, July 26, 2016 1:33 PM

All replies

  • MSP User,

    I am seeing the same thing with Project 2013.

    The best I can suggest is if you are using a custom formula for the RAG status, change the formula to exclude inactive tasks.