  • Hi,

    If I accept a change from external task accidently, I do not see any option to revert my action (accept). I tried Control -Z but did not work.

    1. How to revert my action (accept)?

    2. Is there any option to deny an external link when there is a difference in external task dates?

    Pls suggest

    Tuesday, September 12, 2017 10:03 PM

All replies

  • Sudhir,

    Control-Z (Undo) should work as long as you do it immediately after accepting the link.

    As far as I know there is no option to automatically deny a link when dates don't match. It is up to the user to decide if the link update is valid. Keep in mind that external links are designed to update linked plans and if the user does not "want" to accept the change, coordination between owners of each plan is in order.

    Hope this helps.

    John