  • HI ALL

    I have one pwa site provisioned under one SSP.

     

    I want to create one new SSP and want to restore/migrate the same pwa on this SSP..

     

    I want same PWA to exist on both SSP.

     

    IS it possibel and if yes then how and if no they why?

    Please help,,,,any help would be appreciated


    shashi mishra
    Thursday, May 5, 2011 11:29 AM

Answers

  • Hi Shashi,

    I don't have a project server 2007 system available, but you can host multiple instances of pwa within a multiple SSPs, ie you can have http://servername/PWA1 running within SSPPWA1 and then http://servername/PWA2 running within SSPPWA2.

    The steps for this very broadly would be....

    1.  Backup your existing DBs. (note that depending on the configuration of the WSS_content_DB you may/may not be able to take this data.

    2.  Restore the DBs with different names.

    3.  Create a new web app to host project server, and create a new SSP - details found within this deployment paper - http://technet.microsoft.com/en-gb/library/cc197479(office.12).aspx 

    4.  Provision your new site in the new SSP, using the pre-provisioned DBs previously restored.

     


    Ben Howard [MVP] blog | web
    Thursday, May 5, 2011 1:49 PM