  • Hi,

    While viewing the project detail page of any specific project, the task level custom field indicators doesnot show the relevant threshold indicators and appears to be blank or same value across all the task irrespective of the formula and it always needs a temporary indent and outdent type of workaround to bring the real value in PWA


    Thanks and Regards, Sumit Pandey | Consultant