  • Can anyone explain how do yo get the little arrow to hide a task in MS Project? each time I right click to add a task it becomes a sub task. I would like it to be a main task.
    Wednesday, August 30, 2017 10:32 AM

All replies

  • Hi,

    Select the task and click on the following icon in the task tab of the ribbon.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    Wednesday, August 30, 2017 11:35 AM