how to assign tasks to individuals within teams? RRS feed

  • Question

  • we are wanting to put some subject matter experts in a project team called SME.  We want to assign tasks to the SME team but individuals still record time to their tasks.  Is their a way to have three people in a team, assign a task to the team and then whoever picks it up in the team then record his/her time to a task in his/her my work section so it records it to that person when I see it in my approval section?   

    Cletus51

    Wednesday, September 25, 2013 5:00 PM

Answers

  • The task is assigned to the team pool and the resource then selects the tasks they want to work on and assign it to themselves.  From that point on it becomes their task and you will see their name when approving the timesheet.

    Wednesday, September 25, 2013 7:15 PM

All replies