none
Archived plans still display in task update list RRS feed

  • Question

  • Hi,

    We have recently migrated from MSP 2007 and EPM 2007 to MSP 2010 and EPM 2010. In the task list of a resource, there are still old project plans which have been completed that are displaying, even though the resources have completed all work and the plan in MSP 2010 has been saved as completed with all remaining work zero'd. Why are the old plans still appearing in the task list and cluttering the display even though the project has been marked as completed?

    Thank you,

    Jaco

    Wednesday, June 6, 2012 4:05 PM

All replies