Setting Up Timesheets in Project Online RRS feed

  • Question

  • Is the Timesheet link supposed to automatically be added to the Quick Launch? Or does this need to be manually setup if we want to use Single Entry Mode?

    I assume the link for the Task page needs to also be removed from the quick launch. Is that correct?

    Thanks,

    Roland

    Monday, September 15, 2014 5:31 PM

Answers

  • Hi Roland,

    Indeed if you enable the SEM (single entry mode), I'd suggest you to remove the "task" link and only keep the "timesheet" link in the quick launch.

    You can manually turn off / on the links from PWA Settings > Quick Launch under Look and Feel. 


    Hope this helps,


    Guillaume Rouyre, MBA, MCP, MCTS |

    • Marked as answer by Roland G29 Monday, September 15, 2014 5:45 PM
    Monday, September 15, 2014 5:34 PM
    Moderator

All replies

  • Hi Roland,

    Indeed if you enable the SEM (single entry mode), I'd suggest you to remove the "task" link and only keep the "timesheet" link in the quick launch.

    You can manually turn off / on the links from PWA Settings > Quick Launch under Look and Feel. 


    Hope this helps,


    Guillaume Rouyre, MBA, MCP, MCTS |

    • Marked as answer by Roland G29 Monday, September 15, 2014 5:45 PM
    Monday, September 15, 2014 5:34 PM
    Moderator
  • Great thanks for the info! I thought this was going to be automatically set when selecting SEM