Unable to Map Field Milestone from Project Proffesional 2013 to SharePoint Task Lists RRS feed

  • Question

  • Hi,

     

    I am trying to update SharePoint 2013 Task List, from Microsoft Project Proffesional 2013. When I tried to Map fields, I am unable to find Milestone column in Project Field. Can you update to me what is the problem?

     

    Thank you. 

    Friday, November 15, 2013 8:52 AM

All replies

  • The milestone field in Project is a Yes/No field and is not one of the fields available for mapping by default.  How are you using the milestone field in SharePoint?  Could you map it to one of the Flag fields or perhaps a text field?
    Friday, November 15, 2013 6:18 PM