Unable to drag data in resource plan when there is one resource RRS feed

  • Question

  • BSM Bug - When there is one resource in resource plan , line managers cannot drag data from one cell to another, (it works with more than one resource)

    (Drag the bottom-right corner of a cell to repeat data to other cells)

     

    Repro:-

    1-      Open any project in PWA (QA or Production)

    2-      Go to Project tab > Project Permissions

    3-      Build Team

    4-      Add one resource > save and close

    5-      Add data in one of the fields then try to drag it to other cells

    Results:-

    Data cannot be dragged if there is only one resource.

    


    If there are more than one resource

    i have tested this in two environments getting same results  ,

    Anyone here can test this for me in project server 2010 ?

    Do you think this is a BUG


    Karim El Zarka, MCTS Sharepoint 2010 , MCITP SharePoint Administrator 2010 Whenever you see a reply and if you think is helpful, click "Vote As Helpful"! And whenever you see a reply being an answer to the question of the thread, click "Mark As Answer

    Friday, June 26, 2015 11:42 AM

Answers

  • Hello, 

    I have opened a premier ticket with Microsoft and have received the following back in November 2015 

    Case summary is below;

    ACTION:

    Assume that you have a single resource in a resource plan. You then wish to add timephased data for that resource.

    RESULT:

    In this scenario, the fill handle is not present so data cannot be simply dragged/autofilled.

    If >1 resources are present in the resource plan then the fill handle appears.

     

    CAUSE:

    This is a limitation/bug in Microsoft Project Server 2013.

     

    RESOLUTION:

    A fix request was made but was rejected by the product group


    Karim El Zarka, MCTS Sharepoint 2010 , MCITP SharePoint Administrator 2010 Whenever you see a reply and if you think is helpful, click "Vote As Helpful"! And whenever you see a reply being an answer to the question of the thread, click "Mark As Answer

    • Marked as answer by Karim El Zarka Thursday, September 7, 2017 9:17 AM
    Thursday, September 7, 2017 9:17 AM

All replies

  • With only one resource i'm not able to Drag the bottom-right corner of a cell to repeat data to other cells

    \

    With more than one Resource, i'm able to Drag the bottom-right corner of a cell to repeat data to other cells


    Karim El Zarka, MCTS Sharepoint 2010 , MCITP SharePoint Administrator 2010 Whenever you see a reply and if you think is helpful, click "Vote As Helpful"! And whenever you see a reply being an answer to the question of the thread, click "Mark As Answer

    Friday, June 26, 2015 11:43 AM
  • Hello, 

    I have opened a premier ticket with Microsoft and have received the following back in November 2015 

    Case summary is below;

    ACTION:

    Assume that you have a single resource in a resource plan. You then wish to add timephased data for that resource.

    RESULT:

    In this scenario, the fill handle is not present so data cannot be simply dragged/autofilled.

    If >1 resources are present in the resource plan then the fill handle appears.

     

    CAUSE:

    This is a limitation/bug in Microsoft Project Server 2013.

     

    RESOLUTION:

    A fix request was made but was rejected by the product group


    Karim El Zarka, MCTS Sharepoint 2010 , MCITP SharePoint Administrator 2010 Whenever you see a reply and if you think is helpful, click "Vote As Helpful"! And whenever you see a reply being an answer to the question of the thread, click "Mark As Answer

    • Marked as answer by Karim El Zarka Thursday, September 7, 2017 9:17 AM
    Thursday, September 7, 2017 9:17 AM