My Task Split moves to the end when I join my task back together. RRS feed

Answers

  • Hi,

    Your task type is probably fixed duration. Go to task information, Advanced, to change it into Fixed Units or Fixed Work to make the trailing split disappear.

    Greetings,

    • Marked as answer by bhause Friday, April 29, 2011 11:06 PM
    Friday, April 29, 2011 6:58 AM
    Moderator

All replies

  • Hi,

    Your task type is probably fixed duration. Go to task information, Advanced, to change it into Fixed Units or Fixed Work to make the trailing split disappear.

    Greetings,

    • Marked as answer by bhause Friday, April 29, 2011 11:06 PM
    Friday, April 29, 2011 6:58 AM
    Moderator
  • Thanks Jan.  You Da Man!