none
Create roles within tasks RRS feed

  • Question

  • Hi all,

    I'm new to project, so I may be thinking about this in not a "project" way...  I am setting up a schedule for fieldwork.  The work we do requires around 10 people, working together, each fulfilling different roles (more or less...).  I would like to set up a schedule where each task is a "site" we must visit, and I then assign a resource (person) to each role in that site.  For example, let's say that, for each site, we need Tech1, Tech2, Assitant1, Assistant2, and Masseuse.  Thus, when I set up the schedule, I estimate site 1 will take 10 days to complete, and I assign people to each of those roles.

    Is there a way to do this, or am I thinking of this in a way that would be hard for project to implement?

    Thanks in advance...


    Wednesday, April 18, 2018 3:44 PM

All replies

  • You can think of Team tasks & Team Assignment pool concepts in Project Server/Online.

    https://blogs.technet.microsoft.com/projectsupport/2016/12/02/project-online-new-ways-to-work-with-team-assignments/

    https://www.mpug.com/articles/working-teams-project-onlineproject-server-2013/

    Wednesday, April 18, 2018 4:24 PM