    I've got the next problem, I need from a task whose start date is the project start date move when I change the start date of the project. When I change the start date of the project, the start date of the task should move with the start date of the project. 

    How I can do that ? ¿Can I do it with the finish task of the project?

    Thank you all!!

    Tuesday, April 9, 2019 7:48 PM

All replies

  • Hi, If the following are true then what you want will happen.

    1.  The task is zero percent complete.

    2.  It has no predecessors

    3.  It is autoscheduled

    4.  It's constraint type is ASAP.

    5.  There aren't any predecessors in the path that cannot change due to constraints.

    6.  Levelling isn't set to automatic (if you are using resources).

    There may be another couple of things I've missed, but I would check these first.


    Ben Howard [MVP] | web | blog | book | downloads | P2O

    Tuesday, April 9, 2019 9:20 PM
  • Thank you Ben!

    I'll check this and I hope It runs!!!