Acceleration RRS feed

  • Question

  • How can I change working times of just a single task without affecting all the other tasks that fall on the same day?
    Monday, May 21, 2012 8:17 PM

Answers

  • Hello,

    If you have a resource assigned, you may alter the resource's calendar and project will schedule the task based upon the resource's calendar.  If you don't have a resource assigned, you may create a new calendar (copy the existing project calendar), modify the working time for the single day and then assign the new calendar as a task calendar.

    I hope this helps.

    Julie

    Monday, May 21, 2012 9:04 PM
    Moderator
  • Create a task calendar, if only that task need to be changed for Working Time, refer to link below for creating the Calendar.

    http://office.microsoft.com/en-us/project-help/create-a-calendar-for-a-task-within-project-HA010377765.aspx


    Sapna S

    Tuesday, May 22, 2012 7:36 AM
    Moderator

All replies

  • Hello,

    If you have a resource assigned, you may alter the resource's calendar and project will schedule the task based upon the resource's calendar.  If you don't have a resource assigned, you may create a new calendar (copy the existing project calendar), modify the working time for the single day and then assign the new calendar as a task calendar.

    I hope this helps.

    Julie

    Monday, May 21, 2012 9:04 PM
    Moderator
  • Create a task calendar, if only that task need to be changed for Working Time, refer to link below for creating the Calendar.

    http://office.microsoft.com/en-us/project-help/create-a-calendar-for-a-task-within-project-HA010377765.aspx


    Sapna S

    Tuesday, May 22, 2012 7:36 AM