MS Project 2016 Professional RRS feed

  • Question

  • What does Percentage complete indicate in Project Overview report? If the report indicates that project is 20% complete then how is this figure arrived at? What is the formula which throws this figure?

    Is it the summation of tasks complete as a percentage of total tasks ? If yes then how is the weightage of the tasks taken into account?

    Thursday, September 1, 2016 2:24 AM

All replies

  • Have a look at Jim Askell's White Papers at:

    http://www.msprojectblog.com/MSProjectTips.htm



    --rms www.rmschneider.com

    Thursday, September 1, 2016 5:03 AM
  • The value in the Project Overview report is the Project Summary Task percent complete.  For information on the calculation of % complete for tasks see:

    https://support.office.com/en-us/article/Percent-Complete-fields-84ec5068-4a34-497c-97eb-e12b6dc47cc5

    For summary task calculation see:

    https://support.microsoft.com/en-us/kb/101495

    Thursday, September 1, 2016 10:32 AM
    Moderator