Increasing resource hours RRS feed

  • Question

  • I have 56 hours available in my Mill resource.  How do I get project to recognize it?  Currently anything over 8 hours shows as over allocated
    Wednesday, March 8, 2017 3:14 PM

All replies

  • Hi,

    open your Mill resource from Resource Center for editing and set Max Units to "700" to get 56hrs/day.

    Does that help?
    Barbara


    To increase the value of this forum, please mark the replies that helped to solve your issue as answer. If you find answers to questions from other forum participants to be helpful, please mark them as helpful. Your participation will help others to find an appropriate solution faster. Thanks for your support!