Merge Resources in MS Project RRS feed

  • Question

  • I made an spelling error and ended up with two different resources in my resource sheet. I have corrected the spelling but still shows as two rows in the resource sheet. How can I combine / merge the two so the hours show on one?
    Wednesday, August 17, 2016 1:43 PM

All replies

  • Hi,

    You can simply delete the duplicated resource from the resource sheet, as soon as it has no actual work. Also check before deleting that it has no remaning work (work column) If it has, you can replace the duplicated resource by the correct resource by selecting the assignment, go to "resource" tab, "assign resource" and make a "replace".


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    • Proposed as answer by Jamesse Tuesday, September 10, 2019 1:49 PM
    Saturday, August 20, 2016 11:03 AM
    Moderator
  • I agree with Guillaume, delete the obsolete misspelled resource.

    Since you've "corrected" the spelling error in the Gant Chart - the wrong resource is probably not connected to any task. So you can delete it without any los of information.

    Best Regards

    John Hansleyton | https:\\www.power2plan.com

    Sunday, August 21, 2016 3:51 PM