%WORK Complete in PWA Project Center Gantt?

    Question

  • Is it possible to show %WORK Complete (not %Complete) in the Gantt bars in the Project Center? It appears it may only be possible to show %Complete. I know there is often confusion how these are calculated, but I know many people would like to see a bar that shows % of the work that is completed vs the duration of the project that is represented by the Gannt bar.

    Thanks,

    Daniel

    Thursday, April 20, 2017 9:20 PM