Grouping projects into programs(project server 2010) RRS feed

  • Question

  • Please is it possible to group projects in the project centre into different programs( a collection of realated projects)

    how can this be acheived?

    Tuesday, October 19, 2010 2:55 PM

Answers

  • kehinde Bada --
     
    To do this, your Project Server administrator should create a custom enterprise Project field that lists the names of your company's programs.  Then each PM will need to select a value in this field using the Project Information dialog each time he/she creates a new project.  Then the custom field would need to be added to a default or custom Project Center view with grouping applied to that field.  Hope this helps.

    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Tuesday, October 19, 2010 2:59 PM