Microsoft Project Start & Finish Date being a Duration from Project Commencement Date RRS feed

  • Question

  • I need to schedule ~92 tasks which have a start and finish time based on a number of days from the Project Commencement Date which is currently not known.

    E.g.: Bridge A09 start 101 days from Date of Contract and finish 109 days from Date of Contract. Therefore a duration of 9 days.

    Can this be entered into Microsoft Project so that when the Commencement Date is finalised and entered all the tasks will also alter their start and finish dates while maintaining the duration between them.

    The days are calendar days not work days.

    Please advise, thanks.

    • Moved by Peter GeelenMVP Friday, September 16, 2016 6:21 AM off topic on TNWiki
    Friday, September 16, 2016 2:23 AM

All replies

  • Why are you posting this on the TechNet Wiki forum?

    With the same effort you could have chosen the appropriate forum, and get some helpful answers to your question instead of dumping your question on a unrelated forum. http://letmebingthatforyou.com/?q=ms%20project%20forum

    You must check at : https://social.technet.microsoft.com/Forums/projectserver/en-US/home

    or https://answers.microsoft.com/en-us/msoffice

    or https://social.technet.microsoft.com/Forums/en-US/home?forum=officeitpro

    As stated in the announcements and the sticky posts on this forum, this is the wrong audience for your question.

    To make sure you get an answer, I've moved the post...


    Peter Geelen (Quest for security) (user page)

    [If a post helps to resolve your issue, please click the "Mark as Answer" of that post or click Answered"Vote as helpful" button of that post. By marking a post as Answered or Helpful, you help others find the answer faster. ]


    Friday, September 16, 2016 6:11 AM
  • Hi Ian,

    It is indeed possible, and I would say that it is a best practice in scheduling. In MS Project ribbon, "project" tab, "project information", you can set the project start date.

    Then schedule your 92 tasks with dependencies (links) and not constraints on the start/finish dates. Meaning that you have to create links between tasks and enter a duration, no start date which will create constraints. You should have no "calendar" icons in the indicator column.

    This is the condition for getting what you need : as soon as you know the project start date, just update it in the project information and your entire project will be moved accordingly, keeping the dependencies and durations.


    Hope this helps,