Assigned Material Resource Values changed in Visual Reports RRS feed

  • Question

  • Dear All,

    Please help about title problem as i facing this conflict in my visual reports (e.g i have assigned Material Resource 24 M.ton while its showing 3.1 ton in my visual report i could not find the solution please help0

    Kind Response is requested.

    Thursday, January 10, 2013 7:05 AM

All replies

  • You have a little detective work to do to find out how the 3.1 number is derived. Things to look for are:

    • The time frames in Project vs Visual Reports - for instance, does the project task span year end and the Visual Reports get filtered to show only either 2012 or 2013 - or maybe by week?
    • Actual vs Scheduled vs Baselined - are you comparing the same fields?
    • Total work vs peak units - a variant of the second item above. The treatment of material resources can be a bit confusing since the units and work field both hold the quantity of material but the peak units shows the dailt quantity.

    Happy hunting

                Graham