  • Hi there,

    I'm trying to get my head around resource usage in Project Online. As a test, I've created a project plan in Project Professional with two tasks for the same period, and it's correctly flagging that I've got a problem:

    But when I save and publish the plan, I get no indicators on the online version of the plan:

    And also no issues on the capacity planning heatmap (where I really want issues flagged):

    I'm sure I'm missing something, any advice on how to get the issues to feed through would be much appreciated, any other info needed, let me know, and thanks in advance!

    Tuesday, June 21, 2016 6:13 PM

Answers

  • Hi Daveyboyh,

    Please see this thread, the features/functionality are similar for 2016 and Online resource engagement.


    -SNKBalaji



    • Edited by SNKBALAJI Wednesday, June 22, 2016 6:36 AM
    • Marked as answer by daveyboyh Wednesday, June 22, 2016 7:23 AM
    Wednesday, June 22, 2016 6:35 AM

All replies

  • Hi Daveyboyh,

    Please see this thread, the features/functionality are similar for 2016 and Online resource engagement.


    -SNKBalaji



    • Edited by SNKBALAJI Wednesday, June 22, 2016 6:36 AM
    • Marked as answer by daveyboyh Wednesday, June 22, 2016 7:23 AM
    Wednesday, June 22, 2016 6:35 AM
  • Ahh, thanks. I didn't spot that one. That's a real shame for us 'after the event' resource managers! I might look into whether I can just automatically approve everything using the PSI.

    Thanks for your help!