Remaining Tasks and Remaining Actual Tasks in Microsoft Project Professional 2013 RRS feed

  • Question

  • Hi,

    What is the difference between "Remaining Tasks and Remaining Actual Tasks fields in Milestone report in Microsoft Project Professional 2013?


    K.Gokulraj

    Tuesday, March 1, 2016 3:23 PM

Answers

All replies

  • Hi,

    Remaining actual tasks are those that are not marked as 100% complete.  The image below should help...


    Ben Howard [MVP] | web | blog | book | P2O

    Tuesday, March 1, 2016 7:56 PM
    Moderator
  • The question was not answered. What is the difference between "Remaining Tasks and Remaining Actual Tasks"

    I still don't know the difference because I thought all tasks are actual tasks??? What is a task that is not actual for example?

    Thursday, January 18, 2018 4:08 PM
  • Hi Ron,

    I cannot explain Microsoft's naming of these terms, however the way they use them that remaining tasks gives a burndown chart, and remaining actual tasks gives a burndown of tasks that are 100% complete.  It is best to look at the chart to see the difference.


    Ben Howard [MVP] | web | blog | book | downloads | P2O

    Thursday, January 18, 2018 9:12 PM
    Moderator