none
"Red line" of current day in PWA 2010 RRS feed

  • Question

  • Dear all,

    Is there is any way to have the "red line" of current day in PWA 2010 like Microsoft Project Pro 2010?

    Thanks very much.

    Monday, June 4, 2012 4:16 AM

Answers

All replies

  • Hi There--

    Sorry, but it seems that there is no out of box option available for the current date in Gantt chart. You cannot change the color of the Current Date line in the Gantt Chart of any PWA view. 

    Please see a similar thread:
    http://social.technet.microsoft.com/Forums/zh/projectserver2010general/thread/3b718401-3c33-4a4c-b2d7-d46e82efee7d

    Hope this helps.


    If you found this post helpful, please “Vote as Helpful”. If it answered your question, please “Mark as Answer”. Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82

    • Marked as answer by DoLeVu Monday, June 4, 2012 7:43 AM
    Monday, June 4, 2012 6:08 AM
  • Thanks very much, Amit
    Monday, June 4, 2012 7:43 AM
  • You are welcome :) & Thanks for the feedback.

    Thanks,


    If you found this post helpful, please “Vote as Helpful”. If it answered your question, please “Mark as Answer”. Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82

    Monday, June 4, 2012 8:26 AM