How to change the project type of inprogress project RRS feed

  • General discussion

  • How to change the project type of in-progress project, The project type is Testing and need to change it to basic project plan.
    Tuesday, October 7, 2014 8:43 AM

All replies

  • Hi chaishashi,

    • PWA > 'Server Settings' > 'Change or Restart Workflows'
    • Select your old Enterprise Project Type ('Testing')
    • Add the project to the 'Target List'
    • Select a new 'Enterprise Project Type' ('Basic Project Plan')
    • Click 'OK'

    Hope this helps

    Tuesday, October 7, 2014 9:03 AM
  • Another way is to click on the top right button of the project center ribbon, after selecting the project. Note that this way works for one project at a time whereas toon's reply works for bulk edit.

    Hope this helps,


    Guillaume Rouyre, MBA, MVP, MCP |

    Tuesday, October 7, 2014 11:05 AM
    Moderator
  • Toon,

    Thanks for the information, It worked for me.

    Wednesday, October 15, 2014 11:35 AM
  • Guillaume,

    Thanks for the info, Tried this method and its working.

    Wednesday, October 15, 2014 11:37 AM
  • You're welcome. Please change the thread type from discussion to question to be able to mark any helpful reply as an answer so other users with a similar concern can refer to it.

    Hope this helps,


    Guillaume Rouyre, MBA, MVP, MCP |

    Wednesday, October 15, 2014 12:14 PM
    Moderator