Nice easy one - How do i create a hammock (level of effort) in Project 2003 RRS feed

  • Question

  • Hi,

    I'm used to using Primavera and creating a hammock activity was simple.  Change the activity type, link the start of the hammock as a SS pred on the start milestone, a FF successor on the finish milestone, bunch of sequenced activities in the middle.  Every time the work slips (or comes in !) the finish milestone slips and thus so does the hammock finish date.

    Doesnt seem to work in project and the knowledge base file i found did not work - i either get an OLE error message, or if i try to change the hammock activity a message saying "this field is dynamically linke"

    http://support.microsoft.com/kb/141733

    Any suggestions appreciated

    Thanks

    David


    Thursday, December 6, 2012 1:23 PM

Answers

  • David,

    Go to the MVP website at, http://project.mvps.org/faqs.htm, and take a look at FAQ 19 - Hammock tasks.

    John

    • Marked as answer by DavidCumming Friday, December 7, 2012 5:59 PM
    Thursday, December 6, 2012 3:28 PM

All replies

  • David,

    Go to the MVP website at, http://project.mvps.org/faqs.htm, and take a look at FAQ 19 - Hammock tasks.

    John

    • Marked as answer by DavidCumming Friday, December 7, 2012 5:59 PM
    Thursday, December 6, 2012 3:28 PM
  • This reads like a Summary Task in Project. Otherwise the link John gave you does the trick.

    Rod Gill

    The one and only Project VBA Book

    Rod Gill Project Management

    Thursday, December 6, 2012 7:01 PM
    Moderator
  • This reads like a Summary Task in Project. Otherwise the link John gave you does the trick.

    Rod Gill

    It did, didn't it!

    however, we don't want people assigning resources at the summary level as they won't show up in a report we produce via numerous chunks of code and witchery.

    Thanks all

    David

    Friday, December 7, 2012 6:01 PM