Incorrect mpp values RRS feed

Answers

  • Hi Arun,

    Everything matches perfectly. You simply don't tell Project how much work each resource has to do, nor what their units are - at least not on the excel image you provide. How to fix?Tell Project what you need, it will calculate it as you want. But Project cannot read your mind :-(

    Greetings,

    Friday, February 17, 2012 1:46 PM
    Moderator